Building a house: what to look at before you start and what it really costs

October 2026

How much does it cost to build a house? A 150 m² home with mid-range finishes in Alicante or Murcia currently comes to about 293.500 € including taxes, licence and professional fees, not counting the land. Here we explain where that figure comes from, what to look at on the plot, which studies are needed and how long it takes from the first meeting to getting the keys.

We have written it based on what we explain in our first meetings with people who commission a house from us. We start with what interests people most, the money, and then go step by step.

1. How much it costs to build a house

It is the question everyone asks and the one most often answered badly. The price “per square metre” you hear about is usually just the construction work, and the real cost is considerably higher. This is how we work it out in a first estimate:

  1. Construction of the house. Multiply the built area by a reference cost. In the Valencian Community we use the module from the Instituto Valenciano de la Edificación (IVE), which in June 2026 stands at €950/m². For a detached single-family house, the reference cost depends mainly on the finishes (you can see this in the table below).
  2. External works. Paving, walls, fencing and garden: about €300/m² of landscaped plot.
  3. Extras. Pool (about €25,000–30,000), retaining walls, lift…
  4. Builder's overheads and profit. Around 13% and 6% of the construction cost.
  5. VAT on the works. 10% when it is your own home.
  6. Licence. The construction tax (ICIO) and municipal fees, at most 4% of the construction cost, depending on the town hall.
  7. Professionals and studies. The architect's design and site supervision, the works execution manager (arquitecto técnico), health and safety coordination, topographic survey, geotechnical study and, if desired, a technical inspection body. Plus 21% VAT on these.
Finishes and servicesConstruction cost per m² builtWhat it means
Basic≈ €890/m²Simple, standard materials, minimal services.
Mid-range≈ €1,113/m²What you would expect in a well-built house: good insulation, decent windows and doors and standard finishes.
High-end≈ €1,336/m²Top-quality materials, more services (home automation, underfloor heating, aerothermal heat pump…).

IVE unit construction cost for a detached single-family house of up to 3 storeys and more than 70 m² of usable floor area, using the June 2026 module. It is only the cost of the construction work, without the builder's profit or taxes.

An example with figures

A house of 150 m² built, with mid-range finishes, 100 m² of external works and no pool:

ItemCalculationAmount
Construction of the house150 m² × €1,113/m²166.950 €
External works100 m² × €300/m²30.000 €
Construction cost (PEM)196.950 €
Overheads and builder's profit13 % + 6 %37.420 €
VAT on the works10 %23.440 €
Licence (ICIO and fees)≈ 4% of PEM7.880 €
Architect (design and site supervision)Our fees start at €15,00015.000 €
Building engineer (arquitecto técnico), health and safety, topographic survey and geotechnical study8.000 €
VAT on professional fees21 %4.830 €
Approximate total≈ €1,960/m² built≈ €293,500

The rule of thumb: the total cost is around 1.5 times the bare construction budget. And that still doesn't include the land, the water and electricity connections, the notary and registration of the new build, or the kitchen, furniture or garden.

These are indicative figures to give you an idea, not a quote. With high-end finishes the same house would come close to €340,000, and with basic finishes it would drop to about €250,000. Real prices emerge when builders price a complete construction project.

Three figures before you start

Before we start drawing, we will ask you for three figures: the target budget (the one we design to), the maximum (what you do not want to exceed under any circumstances) and the baseline (the minimum needed to build the house properly without losing quality). And how it will be paid for: with a self-build mortgage, the bank pays against stage certificates and requires a valuation of the project, and that affects the timetable.

2. Before buying the plot

The most expensive mistake is buying a plot and finding out afterwards that it won't take the house you had in mind. Before signing, it is worth checking these things with a professional:

If you send us the cadastral reference before buying, we will tell you what can be built and with what limitations. It is a small consultation that can save a lot of money. We explain it in more detail, with two real cases, in Feasibility study: what to check before buying a plot or a house.

3. The land calls the shots: topographic survey and geotechnical study

Before designing the house you need to know two things about the land: its exact shape and what lies beneath it.

Sometimes the geotechnical study changes the project for the better. We have come across three metres of fill with no bearing capacity: rather than a problem, it was an argument in favour of a basement, because excavating it removes the fill and the house sits directly on the good ground.

Excavación del terreno antes de hacer la cimentación
Excavation before the foundations of a building. Photo: Fons Heijnsbroek · CC0, via Wikimedia Commons.

4. The house: what you need, orientation and light

Before thinking about the façade, you need to list what you need and what you would like: bedrooms, bathrooms, open or closed kitchen, study, utility room, garage, porch, pool. And, above all, put it in order of priority. If cuts had to be made, which three things are untouchable?

Every square metre counts. At current prices, every extra 10 m² of house means about €20,000 more at the end. A compact, well-organised house is usually nicer to live in than a large one full of corridors.

Villa Mairea, de Alvar Aalto, con su jardín delante
Villa Mairea, by Alvar Aalto (Noormarkku, 1939): the house is organised around the garden. Photo: Ninara · CC BY 2.0, via Wikimedia Commons.

Orienting each space

In our climate, orientation is half of comfort. These are the guidelines we usually follow:

SpaceOrientationWhy
BedroomsEast or north-eastThe morning sun wakes you up gently, and at night the room is cool.
KitchenNorth or north-eastA more stable temperature and no excess sun on the work area.
Living and dining roomSouth, east or westPlenty of light, with overhangs or porches that block the high summer sun and let in the low winter sun.
Study or officeNorthEven light and a slightly cooler temperature, good for concentrating.
GarageNorthIt acts as a thermal buffer for the rest of the house.
Bathrooms and utility roomNext to the kitchenWater supply and drainage are grouped together, which is cheaper and causes fewer problems.
Porche profundo de piedra en Can Lis, de Jørn Utzon, que da sombra a la vivienda
Can Lis, by Jørn Utzon (Mallorca, 1972). The deep porches let the light in and block the summer sun. Photo: drz image · CC BY-SA 2.0, via Wikimedia Commons.

Privacy, garden and planting

Light doesn't have to come at the expense of privacy. Setbacks, lattice screens, louvres, high windows or a small courtyard let you have plenty of light without the living room being seen from the street. Since the height of boundary walls is limited by the planning rules, planting does a lot of the work: a deciduous tree gives shade in summer and lets the sun through in winter. It's worth thinking about the garden from the start, not at the end.

Villa Mairea vista entre los árboles del bosque
Villa Mairea, by Alvar Aalto (Noormarkku, 1939), among the trees. Photo: Frans Drewniak · CC BY-SA 2.0, via Wikimedia Commons.

Passive first, then the machines

A well-orientated, well-insulated, airtight house with solar shading and cross-ventilation needs far less heating and cooling. The services (aerothermal heat pump, underfloor heating, solar panels) come afterwards, to complete the design, not to correct a poor one.

Where to invest and where to economise

Better not to cut back (hard to change later)Can be trimmed (easy to upgrade later)
Structure and foundationsSome finishes and claddings
Insulation and waterproofingFurniture and fittings
Windows, doors and glazingGardening and landscaping
Heating, cooling and basic servicesDecorative elements

The materials you breathe count too: lime or water-based paints, natural timber, or cork or wood-fibre insulation are healthy options that can be considered from the design stage.

Aplicación de revestimientos naturales de tierra y cal en una vivienda
Natural earth and lime finishes applied by hand. Photo: Teresempere · CC BY-SA 4.0, via Wikimedia Commons.

5. The steps and the timescales

StageWhat happensApproximate timescale
Survey and data gatheringTopographic survey, geotechnical study and checking the planning rules.3–4 weeks
Preliminary design3D design: layout, volumes, light, materials, pool and garden.6–10 weeks
Basic designWhat defines the house and is submitted to apply for the permit.3–4 weeks
Building permit (licencia de obras)Processing at the town hall.3 to 8 months, depending on the municipality
Construction projectStructure, services, details, quantities and budget. It is prepared while the permit is being processed.In parallel
TenderingQuotes from builders are requested and compared.During the permit
WorksConstruction with site supervision.12–18 months
CompletionFinal completion certificate, first occupancy, Cadastre (Catastro), new build deed (escritura de obra nueva) and Land Registry.1–3 months

From the first meeting to getting the keys, the realistic figure is about two years. The time spent on the permit isn't lost: it's used to finish the construction project and get prices.

Maqueta de la Villa Mairea con la piscina y el jardín
Model of Villa Mairea, by Alvar Aalto. Deciding on the drawing and the model is much cheaper than on site. Photo: 丘崈 · CC0, via Wikimedia Commons.

Our way of working is that decisions are made in the design, not on site. We work in 3D and with a complete construction project before hiring a builder, because every change on site costs dearly in money and time.

6. Who's who

The site supervision is mandatory and safeguards the technical quality. Construction management is a separate, optional service: comparing quotes, coordinating trades, planning and keeping the money under control. One protects the quality; the other, your pocket and your time.

A note on ten-year insurance

If you are building a single home for yourself, the Ley de Ordenación de la Edificación (Building Act) exempts you from ten-year structural insurance (seguro decenal). But if you sell it within ten years, you will have to take it out, or the buyer will have to expressly waive it. If there's any chance you might sell, it's best to decide from the outset.

In short

  1. Look at the plot with a professional before buying it.
  2. Get the topographic survey and geotechnical study done before drawing anything.
  3. List what you need by priority and orientate each space properly.
  4. Work out the total cost, not just the construction: allow 1.5 times the bare construction cost.
  5. Make the decisions in the project and hire the builder with a complete construction project.

If you're thinking of building a house in the province of Alicante or the Region of Murcia, have a look at our new build project service, or write to us via the contact page. The first conversation is about listening to you.